There are available credits but jobs fail for no credits

Hi
The Plan Usage shows: “You have used 0/2,500 credits.”
But builds fail with with “This job has been blocked because no credits are available on your plan. Please upgrade to continue building.”

Thanks,
Rotem,

I think this may be a timezone issue, credits appear to be refilled on Sunday evening in PST. Where are you located?

Now it works.

I’m located in Israel (+2)
Last failed try was at night 00:00 (next day) IST
So there are two issues:

  1. The UI show it calculated as local time
  2. It seems to be at the beginning of the day, and not at the evening

This makes the different of more than 24 hours.