Hold Steps UI Confusion

Visualization of the flows has caused some confusion and is dangerous as it can lead to mistakes with the hold flows. The routing is mixed and does not accurately portray the next/connected steps (see image).

As you can see above “hold-prod” should point to “deploy-production” (which it technically does) but the fact they are on differing levels is pretty confusing and could lead to human error.

Is there any way this can be resolved?

Duplicated by this post.